This section provides a summary page of what's been happening as well as what events or activities are upcoming!
The are four subsections that go into further detail:
- Community - what we have been doing to engage the local residents
- Consultants - experts have we hired to perform our environmental studies
- Studies - contains the full Environmental Impact Statement/ Environmental Screening Report (EIS/ESR)
- Milestones - major milestones achieved throughout the development phase of a wind power project in Ontario
| Activity |
Date |
Detail |
| Wind Monitoring Mast |
7th June 2007 |
Milestone
|
| Notice of Commencement of Environmental Screening |
5th September 2007 |
Milestone
|
| First Public Meeting |
20th September 2007 |
Community
|
| First Public Information Session |
20th September 2007 |
Milestone
|
| Second Public Meeting |
17th June 2008 |
Community
|
| Second Public Information Session |
17th June 2008 |
Milestone
|
| Notice of Completion of Environmental Screening |
26th March 2009 |
Milestone
|
| Municipal Planning |
27th April 2009 |
Milestone
|
|
Construction at Bicker Wind Farm, England |