Many different activities need to be undertaken during the development phase of the project - a selection of key milestones are presented below:

July 2006

Desk based site selection and identification started

August 2006

Initial consultation with the with stakeholders

December 2006

Avian surveys started

June 2007

Installed temporary anemometry mast

June 2007

Avian surveys completed

August 2007

Presentation made to the Town of Kingsville

September 2007

Issued Notice of Commencement of Environmental Screening

September 2007

First Public Information Session held

March 2008

Completion of Stage 1 Archaeology Report

April 2008

Submission of draft EIS/ESR for review

June 2008

Second Public Information Session held

September 2008

Bat surveys completed

Winter 2009

Issued Notice of Completion

Winter 2009

Submission of Final EIS/ESR

Municipal Planning : 27th Apr 2009

Notice of Completion of Environmental Screening : 26th Mar 2009

The Environmental Impact Statement/Environmental Screening Report (EIS/ESR) has been finalized and submitted to the Ontario Ministry of the Environment (MOE). A Notice of Completion was issues on March 26th, 2009. 

Second Public Information Session : 17th Jun 2008

A second public information session was held for the Arner Green Wind Farm on June 17th, 2008 at the Cottam United Church in Cottam.  The purpose of this information session was to provide an update and results from the environmental studies undertaken since the commencement of environmental screening.

For more details on the second public information session, please go to the Community section.

First Public Information Session : 20th Sep 2007

As part of the Notice of Commencement of the Environmental Screening process, the first public meeting was held at the Cottam United Church, in Cottam, on September 20th, 2007, between 5:00 pm and 9:00 pm.  The meeting served as an opportunity for the community to learn about wind energy and the proposed project, as well as an opportunity for us to engage the community in the development process.  There was a pretty good attendance; in total, we had 46 people sign in upon arrival.

For more details on the information provided at the information session, please see the Community section.

Notice of Commencement of Environmental Screening : 5th Sep 2007

Following the early project development and evolution, a Notice of Commencement of Environmental Screening for the proposed project was published in September, 2007. The Notice of Commencement was published in two local newspapers; the Essex Free Press, and the Kingsville Reporter. Notices were also distributed to approximately 2500 homes in and around the project area, as well as to all the relevant agencies and municipalities.

Wind Monitoring Mast : 7th Jun 2007

A wind monitoring mast (also often called an anemometry mast) was installed on June 7, 2007.  The tower is 60 metres in height, and is installed with anemometers and wind vanes at several heights to measure the wind speed and wind direction, respectively.  The data measured will help us to determine the wind resource at the site.

The tower is situated in an agricultural field on land of one of our participating landowners, off Road 9 West.

Canunda wind farm South Australia

Canunda wind farm South Australia

Surfers near Royal Seaforth Wind Farm (UK)

Surfers near Royal Seaforth Wind Farm (UK)

Home - The Wind Farm - Facts & figures - Why here? - Predicted views - Community benefits - What's happening? - Community - Consultants - Studies - Milestones - The process - Wind monitoring - Development - Planning - Construction - Operation - About us - Values & history - How we work - Wind energy - FAQ's - Education - Links - Picture gallery - Contact us - Have your say - Search - Terms, Conditions & Disclaimer

Copyright © 2012 - Wind Prospect Ltd

Content Management System and Database Design BristolContent Management System and Database Design Bristol